Electrical Project Approval, Installation Inspection and Acceptance

PROJECT APPROVAL


The permit, construction site, and final electrical installation project files prepared by your project company must be submitted to the Subscriber Services Department for approval.

INSTALLATION INSPECTION AND ACCEPTANCE

In order for your completed electrical installation, according to the approved project, to be accepted, your project, along with the attachments listed below, must be submitted to the Customer Services Department as an acceptance file by your project company.

ATTACHMENTS:

  • Team Project and Attachments

  • Photocopies of Office Registration and SMM Certificates

  • Copy of Building Permit (Certified True Copy)

  • Numbering Document

  • Building Inspection Service Contract

  • Building Inspection Inspector Certificate

  • Building Inspection Conformity Certificate

  • Grounding Report

  • Contract between Electrician and Company Owner

  • Work Commencement and Completion Documents

  • Notarized Undertaking

WHEN VISITING THE SITE FOR INSTALLATION INSPECTION AND ACCEPTANCE;

  • The grounding resistance value is measured by the project firm.

  • The electrical installation is checked for compliance with the project.

  • If multiple independent units are to be accepted, it is determined that there is a wall between each independent unit; otherwise, a project for combining them to be supplied from a single meter is requested.